Meeting Agenda
|
---|
1. CALL TO ORDER/ROLL CALL
|
2. AUDIENCE TO VISITORS
|
3. APPROVAL OF MINUTES
|
3.a. Facilities Committee Meeting Minutes - JUNE 10, 2025
|
4. DISTRICT ARCHITECT OF RECORD - STUDIOGC architecture+interiors
|
4.a. INFORMATION/DISCUSSION/ACTION: StudioGC architecture+interiors Project(s) Update
|
4.a.I. Todd Hall HVAC Tunnels by Oak Brook Mechanical Substantial completion status met the 8/1/2025 deadline. Insulation application finishing week of 8/11/2025
SD74 to work with Everest on programming |
4.a.II. Sitework by Abbey Construction
Substantial completion status met by 7/25/2025 deadline Striping of play areas scheduled for week of 8/11/2025 Gaga Ball Pit structure to be purchased and installed by SD74 |
4.a.III. General Trades by Construction Solutions, Inc.
Substantial completion status was NOT met by 8/1/2025 deadline; Anticipating SEP 2025 |
4.a.IV. Rutledge Hall Corridor Flooring by Construction Solutions, Inc.
Substantial completion status met by 8/11/2025 deadline Working through punch list items and question about Door #1 walk off mat’s background |
4.a.V. Storage Unit by TuffShed
Concrete foundation cured by AUG 11 Expecting structure in place during week of AUG 11 Access ramps TBD |
4.a.VI. Kindergarten Playground Surface
Anticipated to be ready for student activity on 8/25/2025 |
4.a.VII. Grade 1 Classroom Furniture
All but the lecterns have been delivered and assembled Punch list notes scratches on bands; IFB’s solution TBD Final payment for lecterns to be held until punch list items are completed |
4.a.VIII. Parking Lot Reconfiguration Striping
SD74 seeking quotes from 2 respected contractors that recently completed work on campus |
5. OLD BUSINESS
|
6. NEW BUSINESS
|
6.a. INFORMATION/DISCUSSION/ACTION: 2025-2026 Vivi Players
|
6.b. INFORMATION/DISCUSSION/ACTION: Raptor Technologies, LLC Subscription Agreement
|
6.c. INFORMATION/DISCUSSION/ACTION: Renaissance Communication System Installation of Door Access Control Installation
|
6.d. INFORMATION/DISCUSSION/ACTION: Video Camera Recommendations 2025-2026 School Year
|
7. INFORMATION/DISCUSSION: District Facilities Update
|
7.a. Motorized bikes and scooters
|
7.b. Extra Bricks from Summer 2023 tuckpointing project
|
7.c. Energy Systems Group
|
7.d. Facilities Rental Requests
LBSA for JAN 2026-JUN 2026 Lincolnwood Parks & Recreation for Fall after-school activities Girl Scouts: Todd Hall/Rutledge Hall spaces for year-long Daisies, Brownies & Jr. GS meeting iPro Soccer Todd Hall/Rutledge Hall for NOV 2025-MAR 2026 Skomor Soccer |
8. ADJOURNMENT
|
Agenda Item Details
Reload Your Meeting
|
||
---|---|---|
Meeting: | August 19, 2025 at 6:00 PM - Facilities Committee Meeting | |
Subject: |
1. CALL TO ORDER/ROLL CALL
|
|
Description:
FACILITIES COMMITTEE MEMBERS
John P. Vranas (BOE), Chair Myra A. Foutris, Co-Chair (BOE) Elissa B. Rosenberg (BOE) Emily McCall, Community Member ADMINISTRATORS/STAFF Dr. David L. Russo, Superintendent of Schools Dr. Dominick M. Lupo, Assistant Superintendent for Curriculum & Instruction Courtney L. Whited, Business Manager/CSBO James Caldwell, Sr., Director of Buildings & Grounds |
||
Subject: |
2. AUDIENCE TO VISITORS
|
|
Subject: |
3. APPROVAL OF MINUTES
|
|
Subject: |
3.a. Facilities Committee Meeting Minutes - JUNE 10, 2025
|
|
Description:
Motion by member:________________ Seconded by:____________________
|
||
Attachments:
|
||
Subject: |
4. DISTRICT ARCHITECT OF RECORD - STUDIOGC architecture+interiors
|
|
Subject: |
4.a. INFORMATION/DISCUSSION/ACTION: StudioGC architecture+interiors Project(s) Update
|
|
Attachments:
|
||
Subject: |
4.a.I. Todd Hall HVAC Tunnels by Oak Brook Mechanical Substantial completion status met the 8/1/2025 deadline. Insulation application finishing week of 8/11/2025
SD74 to work with Everest on programming |
|
Subject: |
4.a.II. Sitework by Abbey Construction
Substantial completion status met by 7/25/2025 deadline Striping of play areas scheduled for week of 8/11/2025 Gaga Ball Pit structure to be purchased and installed by SD74 |
|
Subject: |
4.a.III. General Trades by Construction Solutions, Inc.
Substantial completion status was NOT met by 8/1/2025 deadline; Anticipating SEP 2025 |
|
Subject: |
4.a.IV. Rutledge Hall Corridor Flooring by Construction Solutions, Inc.
Substantial completion status met by 8/11/2025 deadline Working through punch list items and question about Door #1 walk off mat’s background |
|
Subject: |
4.a.V. Storage Unit by TuffShed
Concrete foundation cured by AUG 11 Expecting structure in place during week of AUG 11 Access ramps TBD |
|
Subject: |
4.a.VI. Kindergarten Playground Surface
Anticipated to be ready for student activity on 8/25/2025 |
|
Subject: |
4.a.VII. Grade 1 Classroom Furniture
All but the lecterns have been delivered and assembled Punch list notes scratches on bands; IFB’s solution TBD Final payment for lecterns to be held until punch list items are completed |
|
Subject: |
4.a.VIII. Parking Lot Reconfiguration Striping
SD74 seeking quotes from 2 respected contractors that recently completed work on campus |
|
Subject: |
5. OLD BUSINESS
|
|
Subject: |
6. NEW BUSINESS
|
|
Subject: |
6.a. INFORMATION/DISCUSSION/ACTION: 2025-2026 Vivi Players
|
|
Attachments:
|
||
Subject: |
6.b. INFORMATION/DISCUSSION/ACTION: Raptor Technologies, LLC Subscription Agreement
|
|
Attachments:
|
||
Subject: |
6.c. INFORMATION/DISCUSSION/ACTION: Renaissance Communication System Installation of Door Access Control Installation
|
|
Attachments:
|
||
Subject: |
6.d. INFORMATION/DISCUSSION/ACTION: Video Camera Recommendations 2025-2026 School Year
|
|
Attachments:
|
||
Subject: |
7. INFORMATION/DISCUSSION: District Facilities Update
|
|
Attachments:
|
||
Subject: |
7.a. Motorized bikes and scooters
|
|
Subject: |
7.b. Extra Bricks from Summer 2023 tuckpointing project
|
|
Subject: |
7.c. Energy Systems Group
|
|
Subject: |
7.d. Facilities Rental Requests
LBSA for JAN 2026-JUN 2026 Lincolnwood Parks & Recreation for Fall after-school activities Girl Scouts: Todd Hall/Rutledge Hall spaces for year-long Daisies, Brownies & Jr. GS meeting iPro Soccer Todd Hall/Rutledge Hall for NOV 2025-MAR 2026 Skomor Soccer |
|
Subject: |
8. ADJOURNMENT
|
|
Description:
Motion by member: ______________ Seconded by: _________________
|
||
Dr. David L. Russo, Superintendent of Schools Lincolnwood School District 74 is subject to the requirements of the Americans with Disabilities Act of 1990. Individuals with disabilities who plan to attend this meeting and who require certain accommodations in order to allow them to observe and/or participate in this meeting, or who have questions regarding the accessibility of this meeting or facility, are requested to contact the District Office at 847-675-8234 promptly to allow Lincolnwood School District 74 to make reasonable accommodations for those persons. |