Meeting Agenda
I. Call to Order
II. Discussion Items
II.A. Discussion of Summer 2026 Work
II.A.1. MacArthur Timeline and Ancillary Projects
II.A.1.a. Gymnasium Flooring - Specialty Floors
II.A.1.b. Gymnasium Painting - RFP Update
II.A.1.c. Replacement of Gymnasium Stage Accordion Wall
II.A.1.d. Main Office Furniture Replacements
II.A.2. Eisenhower School Update and Timeline
II.A.2.a. Pre-Bid Walkthrough at Eisenhower - Monday, February 16, 2026 @ 10:00 AM
II.A.2.b. Eisenhower Bid Opening - Friday, February 27, 2029 @ 1:00 PM
II.A.2.c. BOE Discussion of Add Alternate Selections - Finance Committee Meeting on Tuesday, March 3, 2026 @ 6:00 PM
II.A.2.d. BOE Award of Bids and Add Alternate Selections for Eisenhower and MacArthur - March 12, 2026 BOE Meeting
II.A.3. Low Voltage Cabling Work - Betsy Ross & Anne Sullivan Schools
II.B. Custodial Staffing Updates
III. Adjournment
Agenda Item Details Reload Your Meeting
Meeting: February 3, 2026 at 8:30 AM - District 23 Buildings & Sites Committee Meeting
Subject:
I. Call to Order
Subject:
II. Discussion Items
Subject:
II.A. Discussion of Summer 2026 Work
Description:
Amy and Luis have prepared a preliminary Project Tracker that illustrates the upcoming projects being managed by the district this summer. As available, proposals and renderings have been included for review. Amounts shown are estimates and projects will be prioritized based on budgetary availability.
Attachments:
Subject:
II.A.1. MacArthur Timeline and Ancillary Projects
Description:
We are excited to start the work at MacArthur. The timeline has been established as follows: 
Start - June 8, 2026
Substantial Completion - August 1, 2026
Final Completion - August 10, 2026
Subject:
II.A.1.a. Gymnasium Flooring - Specialty Floors
Description:
Proposals for the repainting and refinishing have been attached along with a final rendering as designed by the Mac team.
Attachments:
Subject:
II.A.1.b. Gymnasium Painting - RFP Update
Description:
The RFP for MacArthur Gymnasium Painting was issued and a site visit was conducted last week. Proposals are due Monday. Amy will be prepared to share pricing on Tuesday.
Subject:
II.A.1.c. Replacement of Gymnasium Stage Accordion Wall
Description:
Proposals for two options for the replacement of the brown accordion wall on the stage are attached along with a rendering.
Attachments:
Subject:
II.A.1.d. Main Office Furniture Replacements
Description:
The MacArthur Main office will be re-finished with new furniture and paint. Proposals are attached for the design layout as selected by the Mac office team.
Attachments:
Subject:
II.A.2. Eisenhower School Update and Timeline
Description:
As we work towards Bid distribution and opening, we wanted to share a timeframe as well as opportunities for Board participation and dialogue around some of the add-alternate options.
Subject:
II.A.2.a. Pre-Bid Walkthrough at Eisenhower - Monday, February 16, 2026 @ 10:00 AM
Subject:
II.A.2.b. Eisenhower Bid Opening - Friday, February 27, 2029 @ 1:00 PM
Subject:
II.A.2.c. BOE Discussion of Add Alternate Selections - Finance Committee Meeting on Tuesday, March 3, 2026 @ 6:00 PM
Subject:
II.A.2.d. BOE Award of Bids and Add Alternate Selections for Eisenhower and MacArthur - March 12, 2026 BOE Meeting
Subject:
II.A.3. Low Voltage Cabling Work - Betsy Ross & Anne Sullivan Schools
Description:
As previously discussed with the Board, we will be continuing with our Low Voltage Network Cabling over the summer at Ross and Sullivan. Much of this work is eligible for rate reimbursement and has been solicited as such. The recommendation will be to award the contract to Greatline. Their proposal has been attached.
Attachments:
Subject:
II.B. Custodial Staffing Updates
Description:
Amy & Luis will provide an update on two custodial team members currently on FMLA and the plan to address the staffing needs.
Subject:
III. Adjournment

Web Viewer