I. 2006 and 2008 BOND PROGRAM and LOCAL CONSTRUCTION PROJECT
I.1. Elementary Track Projects – Javier Hinojosa Civil Engineering
I.1.a. Status Report – Drainage O’Grady Elementary
I.2. Elementary Tracks – Sidewalks – Javier Hinojosa Civil Engineering
I.2.a. Status Report
I.2.b. Consideration and Approval of Final Drawings for the Elementary Track Sidewalks
I.3. Tennis Court Project at Veterans Memorial High School (VMHS) – Javier Hinojosa Civil Engineering
I.3.a. Status Report
I.3.b. Consideration and Approval of Final Drawings for the Tennis Court Project at VMHS
I.4. Tom Landry Stadium New Restroom Facilities Project – EGV Architects
I.4.a. Status Report
I.5. Mission Collegiate High School – EGV Architects
I.5.a. Status Report
I.5.b. Consideration and Approval of CCD #05 and Change Order #05 for Credits for the Mission Collegiate High School
I.6. Central Office Administration Project –EGV Architects
I.6.a. Status Report









I.7. Mission Junior High School (MJHS) Kitchen/Dining Addition/Renovations Project – PBK Architects
I.7.a. Status Report
I.7.b. Consideration and Approval of CPR #10 for Five (5) Weather Delay Days for the MJHS Kitchen/Dining Addition/Renovations Project
I.8. Fire/Security Alarm & Intercom System for MJHS High – PBK Architects
I.8.a. Status Report
I.9. New AG Barn Facilities Project– PBK Architects
I.9.a. Status Report
I.9.b. Consideration and Approval of CPR #07 for Eight (8) Weather Delay Days for the New AG Barn Facilities Project
I.10. Mission High School (MHS) Phase III Renovation Project – PBK Architects
I.10.a. Status Report
I.10.b. Consideration and Approval of Final Documents for the MHS Phase III Renovation Project
I.10.c. 2006 & 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
II. Informational
II.1. Swimming Pool – Memorandum of Understanding (MOU) with the City of Mission (Pending)
II.2. Tom Landry Stadium Press Box and Bleacher Project – Update
II.3. School Marquee Project
II.3.a. Status Report
II.3.b. Consideration and Approval of Project and Proposed Budget for the School Marquee Project (Presented by Mr. Roosevelt Rios)
II.3.c. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposal for the School Marquee Project
II.3.d. Consideration and Approval of utilizing our on-call Structural Engineering Services for the School Marquee Project
II.4. MHS and VMHS Scoreboard Installation
II.4.a. Status Report
II.4.b. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposal for the MHS and VMHS Scoreboard Installation
II.4.c. Consideration and Approval of utilizing our on-call Structural Engineering Services for the MHS and VMHS Scoreboard Installation






II.5. Escobar/Rios Elementary Playground Equipment Installation Update
II.5.a. Status Report
II.5.b. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposal for the Escobar/Rios Elementary Playground Equipment Installation
II.5.c. Consideration and Approval of utilizing our on-call Structural Engineering Services for the Escobar/Rios Elementary Playground Equipment Installation
Agenda Item Details Reload Your Meeting
Meeting: February 3, 2016 at 6:00 PM - Facilities Committee
Subject:
I. 2006 and 2008 BOND PROGRAM and LOCAL CONSTRUCTION PROJECT
Subject:
I.1. Elementary Track Projects – Javier Hinojosa Civil Engineering
Subject:
I.1.a. Status Report – Drainage O’Grady Elementary
Subject:
I.2. Elementary Tracks – Sidewalks – Javier Hinojosa Civil Engineering
Subject:
I.2.a. Status Report
Subject:
I.2.b. Consideration and Approval of Final Drawings for the Elementary Track Sidewalks
Subject:
I.3. Tennis Court Project at Veterans Memorial High School (VMHS) – Javier Hinojosa Civil Engineering
Subject:
I.3.a. Status Report
Subject:
I.3.b. Consideration and Approval of Final Drawings for the Tennis Court Project at VMHS
Subject:
I.4. Tom Landry Stadium New Restroom Facilities Project – EGV Architects
Subject:
I.4.a. Status Report
Subject:
I.5. Mission Collegiate High School – EGV Architects
Subject:
I.5.a. Status Report
Subject:
I.5.b. Consideration and Approval of CCD #05 and Change Order #05 for Credits for the Mission Collegiate High School
Subject:
I.6. Central Office Administration Project –EGV Architects
Subject:
I.6.a. Status Report









Subject:
I.7. Mission Junior High School (MJHS) Kitchen/Dining Addition/Renovations Project – PBK Architects
Subject:
I.7.a. Status Report
Subject:
I.7.b. Consideration and Approval of CPR #10 for Five (5) Weather Delay Days for the MJHS Kitchen/Dining Addition/Renovations Project
Subject:
I.8. Fire/Security Alarm & Intercom System for MJHS High – PBK Architects
Subject:
I.8.a. Status Report
Subject:
I.9. New AG Barn Facilities Project– PBK Architects
Subject:
I.9.a. Status Report
Subject:
I.9.b. Consideration and Approval of CPR #07 for Eight (8) Weather Delay Days for the New AG Barn Facilities Project
Subject:
I.10. Mission High School (MHS) Phase III Renovation Project – PBK Architects
Subject:
I.10.a. Status Report
Subject:
I.10.b. Consideration and Approval of Final Documents for the MHS Phase III Renovation Project
Subject:
I.10.c. 2006 & 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
Subject:
II. Informational
Subject:
II.1. Swimming Pool – Memorandum of Understanding (MOU) with the City of Mission (Pending)
Subject:
II.2. Tom Landry Stadium Press Box and Bleacher Project – Update
Subject:
II.3. School Marquee Project
Subject:
II.3.a. Status Report
Subject:
II.3.b. Consideration and Approval of Project and Proposed Budget for the School Marquee Project (Presented by Mr. Roosevelt Rios)
Subject:
II.3.c. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposal for the School Marquee Project
Subject:
II.3.d. Consideration and Approval of utilizing our on-call Structural Engineering Services for the School Marquee Project
Subject:
II.4. MHS and VMHS Scoreboard Installation
Subject:
II.4.a. Status Report
Subject:
II.4.b. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposal for the MHS and VMHS Scoreboard Installation
Subject:
II.4.c. Consideration and Approval of utilizing our on-call Structural Engineering Services for the MHS and VMHS Scoreboard Installation






Subject:
II.5. Escobar/Rios Elementary Playground Equipment Installation Update
Subject:
II.5.a. Status Report
Subject:
II.5.b. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposal for the Escobar/Rios Elementary Playground Equipment Installation
Subject:
II.5.c. Consideration and Approval of utilizing our on-call Structural Engineering Services for the Escobar/Rios Elementary Playground Equipment Installation