skip to main content
Meeting Agenda
I. 2008 BOND PROGRAM & LOCAL CONSTRUCTION PROJECT
I.1. Elementary Track Projects – Javier Hinojosa Civil Engineering
I.1.a. Status Report
I.1.b. Consideration and Approval of Change Order #05 for Thirteen (13) Additional Weather Days for the Elementary Track Projects
I.1.c. Consideration and Approval to Grant Administration Authority to Approve Substantial Completion for the Bryan, Midkiff, Leal and Pearson Elementary Track Projects
I.1.d. Consideration and Approval of Final Completion, Less Betterment Fund Allowance and Final Payment, Less Liquidated Damages for the O’Grady, Escobar-Rios, Marcell, Mims and Castro Elementary Track Projects
I.2. Tennis Court Project at Veterans Memorial High School (VMHS) – J. Hinojosa Civil Engineering
I.2.a. Status Report
I.3. Mission Collegiate High School Project – EGV Architects
I.3.a. Status Report
I.3.b. Consideration and Approval to Grant Administration Authority to Approve Final Completion, Less Betterment Fund Allowance and Final Payment, Less Liquidated Damages for the Mission Collegiate High School Project
I.4. Tom Landry Stadium New Restroom Facilities Project – EGV Architects
I.4.a. Status Report
I.4.b. Consideration and Approval to Reject All Proposals and Re-Advertise for the Tom Landry Stadium New Restroom Facilities Project


I.5. Mission Junior High School (MJHS) and Alton Memorial Junior High School (AMJHS) Canopies Project – PBK Architects
I.5.a. Status Report
I.5.b. Consideration and Approval of Final Completion, Less Betterment Fund Allowance and Final Payment, Less Liquidated Damages for the MJHS and AMJHS Canopies Project
I.6. MJHS Kitchen/Dining Addition/Renovations Project – PBK Architects
I.6.a. Status Report
I.7. New AG Barn Facilities Project– PBK Architects
I.7.a. Status Report
I.7.b. Consideration and Approval for Revised Contract with D. Wilson Construction for the AG Barn Project
I.8. Child Nutrition Program (CNP) Expansion Project – PBK Architect
I.8.a. Status Report
I.8.b. Consideration and Approval to Approve Substantial Completion for the CNP Expansion Project
I.9. Mission High School Phase III Renovation Project – PBK Architects
I.9.a. Status Report
I.9.b. Consideration and Approval of Change Proposal Request #4 to Re-connect HVAC for Building D for the Mission High School Phase III Renovation – Demolition & Infrastructure Project
I.10. 2006 and 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
II. Informational
II.1. Elementary Tracks - Sidewalks
II.1.a. Consideration and Approval of Project and Proposed Budget for Sidewalks to the Elementary Tracks
II.1.b. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposals for Sidewalks to the Elementary Tracks
II.1.c. Consideration and Approval for the Selection of Engineering Services for Sidewalks to the Elementary Tracks
II.2. City of Mission Sidewalk Assistance
II.3. 2014-2015 End of the Year Teamwork’s Work-Order Report
III. Adjournment
Agenda Item Details Reload Your Meeting
Meeting: October 7, 2015 at 6:00 PM - Facilities Committee
Subject:
I. 2008 BOND PROGRAM & LOCAL CONSTRUCTION PROJECT
Subject:
I.1. Elementary Track Projects – Javier Hinojosa Civil Engineering
Subject:
I.1.a. Status Report
Subject:
I.1.b. Consideration and Approval of Change Order #05 for Thirteen (13) Additional Weather Days for the Elementary Track Projects
Subject:
I.1.c. Consideration and Approval to Grant Administration Authority to Approve Substantial Completion for the Bryan, Midkiff, Leal and Pearson Elementary Track Projects
Subject:
I.1.d. Consideration and Approval of Final Completion, Less Betterment Fund Allowance and Final Payment, Less Liquidated Damages for the O’Grady, Escobar-Rios, Marcell, Mims and Castro Elementary Track Projects
Subject:
I.2. Tennis Court Project at Veterans Memorial High School (VMHS) – J. Hinojosa Civil Engineering
Subject:
I.2.a. Status Report
Subject:
I.3. Mission Collegiate High School Project – EGV Architects
Subject:
I.3.a. Status Report
Subject:
I.3.b. Consideration and Approval to Grant Administration Authority to Approve Final Completion, Less Betterment Fund Allowance and Final Payment, Less Liquidated Damages for the Mission Collegiate High School Project
Subject:
I.4. Tom Landry Stadium New Restroom Facilities Project – EGV Architects
Subject:
I.4.a. Status Report
Subject:
I.4.b. Consideration and Approval to Reject All Proposals and Re-Advertise for the Tom Landry Stadium New Restroom Facilities Project


Subject:
I.5. Mission Junior High School (MJHS) and Alton Memorial Junior High School (AMJHS) Canopies Project – PBK Architects
Subject:
I.5.a. Status Report
Subject:
I.5.b. Consideration and Approval of Final Completion, Less Betterment Fund Allowance and Final Payment, Less Liquidated Damages for the MJHS and AMJHS Canopies Project
Subject:
I.6. MJHS Kitchen/Dining Addition/Renovations Project – PBK Architects
Subject:
I.6.a. Status Report
Subject:
I.7. New AG Barn Facilities Project– PBK Architects
Subject:
I.7.a. Status Report
Subject:
I.7.b. Consideration and Approval for Revised Contract with D. Wilson Construction for the AG Barn Project
Subject:
I.8. Child Nutrition Program (CNP) Expansion Project – PBK Architect
Subject:
I.8.a. Status Report
Subject:
I.8.b. Consideration and Approval to Approve Substantial Completion for the CNP Expansion Project
Subject:
I.9. Mission High School Phase III Renovation Project – PBK Architects
Subject:
I.9.a. Status Report
Subject:
I.9.b. Consideration and Approval of Change Proposal Request #4 to Re-connect HVAC for Building D for the Mission High School Phase III Renovation – Demolition & Infrastructure Project
Subject:
I.10. 2006 and 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
Subject:
II. Informational
Subject:
II.1. Elementary Tracks - Sidewalks
Subject:
II.1.a. Consideration and Approval of Project and Proposed Budget for Sidewalks to the Elementary Tracks
Subject:
II.1.b. Consideration and Approval of Procurement Method, Selection, Criteria, Review and Ranking Committee, Wage Rate and Authorization to Seek Proposals for Sidewalks to the Elementary Tracks
Subject:
II.1.c. Consideration and Approval for the Selection of Engineering Services for Sidewalks to the Elementary Tracks
Subject:
II.2. City of Mission Sidewalk Assistance
Subject:
II.3. 2014-2015 End of the Year Teamwork’s Work-Order Report
Subject:
III. Adjournment

Web Viewer