I. 2008 BOND PROGRAM and LOCAL CONSTRUCTION PROJECT
I.1. Mission Junior High School (MJHS) and Alton Memorial Junior High School ( AMJHS) Canopies Project – PBK Architects
I.1.a. Status Report
I.2. MJHS Kitchen/Dining Addition/Renovations Project – PBK Architects
I.2.a. Status Report
I.3. Veterans Memorial High School (VMHS) Cosmetology Lab Project – PBK Architects
I.3.a. Status Report
I.4. New AG Barn Facilities Project– PBK Architects
I.4.a. Status Report
I.5. Child Nutrition Program (CNP) Expansion Project – PBK Architect
I.5.a. Status Report
I.5.b. Consideration and Approval of Change Order #01 for Additional Weather Day for the CNP Expansion Project
I.6. Mission High School (MHS) Phase III Renovation Project – PBK Architects
I.6.a. Status Report
I.7. Mission Collegiate High School Project – EGV Architects
I.7.a. Status Report
I.7.b. Consideration and Approval of Change Proposal #15 for Installation of a Pressure Pump for the Fire Sprinkler System for the Mission Collegiate High School Project
I.8. Tom Landry Stadium New Restroom Facilities Project – EGV Architects
I.8.a. Status Report


I.9. New Central Office Administrative Building Project – EGV Architects  and J. Hinojosa Civil Engineering
I.9.a. Status Report
I.10. Elementary Track Projects – J. Hinojosa Civil Engineering
I.10.a. Status Report
I.11. 2006 and 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
II. Informational
II.1. Swimming Pool Memorandum of Understanding (MOU) with City of Mission
II.1.a. Discussion of the City of Mission and Mission CISD Memorandum of Understanding (MOU) for Engineering and Design Services at the North Side Swimming Pool
Agenda Item Details Reload Your Meeting
Meeting: February 4, 2015 at 6:30 PM - Facilities Committee
Subject:
I. 2008 BOND PROGRAM and LOCAL CONSTRUCTION PROJECT
Subject:
I.1. Mission Junior High School (MJHS) and Alton Memorial Junior High School ( AMJHS) Canopies Project – PBK Architects
Subject:
I.1.a. Status Report
Subject:
I.2. MJHS Kitchen/Dining Addition/Renovations Project – PBK Architects
Subject:
I.2.a. Status Report
Subject:
I.3. Veterans Memorial High School (VMHS) Cosmetology Lab Project – PBK Architects
Subject:
I.3.a. Status Report
Subject:
I.4. New AG Barn Facilities Project– PBK Architects
Subject:
I.4.a. Status Report
Subject:
I.5. Child Nutrition Program (CNP) Expansion Project – PBK Architect
Subject:
I.5.a. Status Report
Subject:
I.5.b. Consideration and Approval of Change Order #01 for Additional Weather Day for the CNP Expansion Project
Subject:
I.6. Mission High School (MHS) Phase III Renovation Project – PBK Architects
Subject:
I.6.a. Status Report
Subject:
I.7. Mission Collegiate High School Project – EGV Architects
Subject:
I.7.a. Status Report
Subject:
I.7.b. Consideration and Approval of Change Proposal #15 for Installation of a Pressure Pump for the Fire Sprinkler System for the Mission Collegiate High School Project
Subject:
I.8. Tom Landry Stadium New Restroom Facilities Project – EGV Architects
Subject:
I.8.a. Status Report


Subject:
I.9. New Central Office Administrative Building Project – EGV Architects  and J. Hinojosa Civil Engineering
Subject:
I.9.a. Status Report
Subject:
I.10. Elementary Track Projects – J. Hinojosa Civil Engineering
Subject:
I.10.a. Status Report
Subject:
I.11. 2006 and 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
Subject:
II. Informational
Subject:
II.1. Swimming Pool Memorandum of Understanding (MOU) with City of Mission
Subject:
II.1.a. Discussion of the City of Mission and Mission CISD Memorandum of Understanding (MOU) for Engineering and Design Services at the North Side Swimming Pool