Meeting Agenda
|
---|
I. 2006 BOND PROGRAM
|
I.1. Marcell Elementary Chiller Replacement Project Tabulation/Evaluation/Ranking
|
I.2. Veterans Memorial High School Chiller Replacement Progress Report
|
I.3. Fire Alarm Project Update for Mims Elementary, O’Grady Elementary and K. White Junior High School
|
I.4. 2006 Financial Update – If Available
|
II. 2008 BOND PROGRAM
|
II.1. 2008 Monies Allocated for New Elementary School
|
II.1.a. Status of TEA Amendment
|
II.1.b. Amount of Re-Allocation for Mission High School Renovations
|
II.1.c. Re-Allocation of Remaining Funds
|
II.1.d. Authorization to Proceed with Architects Contract with ERO International Pending TEA Amendment Approval of Re-Allocation of Funds
|
II.2. K. White Junior High Kitchen Renovation Progress Report
|
II.2.a. Status Report
|
II.3. Waitz Elementary Kitchen Renovation Progress Report
|
II.3.a. Status Report
|
II.4. Veterans Memorial High School Science/Math Classroom Additions Progress Report
|
II.4.a. Status Report – Progress Timeline
|
II.4.b. Chiller Pad Status
|
II.4.c. Consideration and Approval of Requested Project Delay Days
|
II.5. Alton Elementary Renovations Progress Report
|
II.5.a. Status Report – Progress Timeline
|
II.6. 2008 Financial Update – If Available
|
III. Others
|
III.1. Central Boiler Kitchen – Status Report
|
III.2. Drainage
|
III.2.a. Leal Elementary School – Status Report
|
III.2.b. Veterans Memorial High School Courtyard – Status Report
|
III.3. Score – AEP Incentive Checks
|
Agenda Item Details
Reload Your Meeting
|
||
---|---|---|
Meeting: | November 2, 2011 at 6:30 PM - Facilities Committee | |
Subject: |
I. 2006 BOND PROGRAM
|
|
Subject: |
I.1. Marcell Elementary Chiller Replacement Project Tabulation/Evaluation/Ranking
|
|
Subject: |
I.2. Veterans Memorial High School Chiller Replacement Progress Report
|
|
Subject: |
I.3. Fire Alarm Project Update for Mims Elementary, O’Grady Elementary and K. White Junior High School
|
|
Subject: |
I.4. 2006 Financial Update – If Available
|
|
Subject: |
II. 2008 BOND PROGRAM
|
|
Subject: |
II.1. 2008 Monies Allocated for New Elementary School
|
|
Subject: |
II.1.a. Status of TEA Amendment
|
|
Subject: |
II.1.b. Amount of Re-Allocation for Mission High School Renovations
|
|
Subject: |
II.1.c. Re-Allocation of Remaining Funds
|
|
Subject: |
II.1.d. Authorization to Proceed with Architects Contract with ERO International Pending TEA Amendment Approval of Re-Allocation of Funds
|
|
Subject: |
II.2. K. White Junior High Kitchen Renovation Progress Report
|
|
Subject: |
II.2.a. Status Report
|
|
Subject: |
II.3. Waitz Elementary Kitchen Renovation Progress Report
|
|
Subject: |
II.3.a. Status Report
|
|
Subject: |
II.4. Veterans Memorial High School Science/Math Classroom Additions Progress Report
|
|
Subject: |
II.4.a. Status Report – Progress Timeline
|
|
Subject: |
II.4.b. Chiller Pad Status
|
|
Subject: |
II.4.c. Consideration and Approval of Requested Project Delay Days
|
|
Subject: |
II.5. Alton Elementary Renovations Progress Report
|
|
Subject: |
II.5.a. Status Report – Progress Timeline
|
|
Subject: |
II.6. 2008 Financial Update – If Available
|
|
Subject: |
III. Others
|
|
Subject: |
III.1. Central Boiler Kitchen – Status Report
|
|
Subject: |
III.2. Drainage
|
|
Subject: |
III.2.a. Leal Elementary School – Status Report
|
|
Subject: |
III.2.b. Veterans Memorial High School Courtyard – Status Report
|
|
Subject: |
III.3. Score – AEP Incentive Checks
|