skip to main content
Meeting Agenda
1. CALL TO ORDER/QUORUM
2. PLEDGE OF ALLEGIANCE
3. INVOCATION
4. PUBLIC COMMENTS
5. MEETING MINUTES
6. APPROVAL OF TRAVEL
7. FINANCIAL REPORT
7.A. DISBURSEMENTS
7.B. PROGRESS PAYMENTS
 
7.B.1. BALCH & BINGHAM, LLP / 18-FD-04

          FILL PERMIT CHALLENGE - $ 411.25
          GENERAL LEGAL SERVICES - $ 5,056.25
          YILPORT LITIGATION - $ 3,701.25
        
          TOTAL BALCH & BINGHAM - $ 9,168.75

 
7.B.2. DREDGING PROFESSOR, LLC / 23-EN-03

          DEEPENING & WIDENING CONSULTING - $ 720.00
 
7.B.3. HDR ENGINEERING, INC. / 24-EN-04

CLEAN PORTS GRANT APPLICATION - WORK ORDER 2 - $ 6,537.00

 
7.B.4. MP DESIGN GROUP / 22-EN-02

ACCESS ROAD PROJECT (MARAD) - $ 4,343.39

 
7.B.5. MP DESIGN GROUP / 23-EN-01

GENERAL ENGINEERING - WORK ORDER 1 - $ 6,393.38
REEFER PLUG ELEVATION (FEMA) - WORK ORDER 2 - $ 2,101.88
USM/NOAA PIERS (GCRF) - WORK ORDER 4 - $ 15,689.65
ASSET MANAGEMENT/INSPECTION PROGRAM - WORK ORDER 6 - $ 840.00
NEW TUGBOAT PIER (E PIER EXPANSION) - WORK ORDER 7 - $ 1,749.80
CHANNEL DEEPENING & WIDENING FEASIBILITY - WORK ORDER 8 - $ 1,527.50
SHED 50 FIRE PROTECTION & REPAIRS - WORK ORDER 9 - $ 25,298.85

TOTAL MP DESIGN GROUP - $ 53,601.06

 
7.B.6. WARREN PAVING, INC. / 22-EN-03

PAVING - TRAILER LANDING GEAR - PHASE 1 - WORK ORDER 6 - $ 24,206.22
PAVING - TRAILER LANDING GEAR - PHASE 3 - WORK ORDER 7 - $ 347,306.60

TOTAL WARREN PAVING - $ 371,512.82

 
7.B.7. DNP, INC. / 23-EN-04

ELEVATED REEFER PLUGS (FEMA) - $ 27,150.00

 
8. OLD BUSINESS
 
8.A. (EL) AUTHORIZATION TO ADD ADDITIONAL FUNDING TO THE USACE DEEPENING & WIDENING FEASIBILITY STUDY
 
8.B. (JB) APPROVAL TO REJECT PROPOSALS RECEIVED FOR CONSTRUCTION MATERIALS TESTING
 
9. NEW BUSINESS
 
9.A. (EL) APPROVAL OF RESOLUTION NO. 24-06 AUTHORIZING THE MSPA TO ALLOCATE AND EXPEND MATCHING FUNDS FOR THE EXCLUSIVE USE OF PROJECTS BEING PURSUED AND APPLIED FOR BY THE MSPA UNDER THE EPA CLEAN PORTS GRANT PROGRAMS
 
9.B. (JB) APPROVAL TO ADVERTISE A REQUEST FOR QUALIFICATIONS FOR GEOTECHNICAL ENGINEERING AND CONSTRUCTION MATERIALS TESTING SERVICES
 
10. ENGINEERING UPDATE
11. OPERATIONS REPORT
12. EXECUTIVE DIRECTOR'S REPORT
13. GENERAL COUNSEL'S REPORT
14. MDA COMMENTS
15. COMMISSIONERS' COMMENTS
16. EXECUTIVE SESSION - LEGAL MATTER
Agenda Item Details Reload Your Meeting
Meeting: May 23, 2024 at 9:00 AM - Regular Meeting
Subject:
1. CALL TO ORDER/QUORUM
Subject:
2. PLEDGE OF ALLEGIANCE
Subject:
3. INVOCATION
Subject:
4. PUBLIC COMMENTS
Subject:
5. MEETING MINUTES
Subject:
6. APPROVAL OF TRAVEL
Subject:
7. FINANCIAL REPORT
Subject:
7.A. DISBURSEMENTS
Subject:
7.B. PROGRESS PAYMENTS
 
Subject:
7.B.1. BALCH & BINGHAM, LLP / 18-FD-04

          FILL PERMIT CHALLENGE - $ 411.25
          GENERAL LEGAL SERVICES - $ 5,056.25
          YILPORT LITIGATION - $ 3,701.25
        
          TOTAL BALCH & BINGHAM - $ 9,168.75

 
Subject:
7.B.2. DREDGING PROFESSOR, LLC / 23-EN-03

          DEEPENING & WIDENING CONSULTING - $ 720.00
 
Subject:
7.B.3. HDR ENGINEERING, INC. / 24-EN-04

CLEAN PORTS GRANT APPLICATION - WORK ORDER 2 - $ 6,537.00

 
Subject:
7.B.4. MP DESIGN GROUP / 22-EN-02

ACCESS ROAD PROJECT (MARAD) - $ 4,343.39

 
Subject:
7.B.5. MP DESIGN GROUP / 23-EN-01

GENERAL ENGINEERING - WORK ORDER 1 - $ 6,393.38
REEFER PLUG ELEVATION (FEMA) - WORK ORDER 2 - $ 2,101.88
USM/NOAA PIERS (GCRF) - WORK ORDER 4 - $ 15,689.65
ASSET MANAGEMENT/INSPECTION PROGRAM - WORK ORDER 6 - $ 840.00
NEW TUGBOAT PIER (E PIER EXPANSION) - WORK ORDER 7 - $ 1,749.80
CHANNEL DEEPENING & WIDENING FEASIBILITY - WORK ORDER 8 - $ 1,527.50
SHED 50 FIRE PROTECTION & REPAIRS - WORK ORDER 9 - $ 25,298.85

TOTAL MP DESIGN GROUP - $ 53,601.06

 
Subject:
7.B.6. WARREN PAVING, INC. / 22-EN-03

PAVING - TRAILER LANDING GEAR - PHASE 1 - WORK ORDER 6 - $ 24,206.22
PAVING - TRAILER LANDING GEAR - PHASE 3 - WORK ORDER 7 - $ 347,306.60

TOTAL WARREN PAVING - $ 371,512.82

 
Subject:
7.B.7. DNP, INC. / 23-EN-04

ELEVATED REEFER PLUGS (FEMA) - $ 27,150.00

 
Subject:
8. OLD BUSINESS
 
Subject:
8.A. (EL) AUTHORIZATION TO ADD ADDITIONAL FUNDING TO THE USACE DEEPENING & WIDENING FEASIBILITY STUDY
 
Description:
MSPA staff seeks Board authorization to add an additional $300,000.00 to its Feasibility Cost Share agreement with the US Army Corps of Engineers (USACE).  The feasibility study is being completed on a 50/50 cost share with the Federal Government. By providing the funding on an accelerated timeline, the USACE is able to continue working on the study and avoid any pauses that may be caused by delays in the appropriation of Federal funding. The entire study is anticipated to take three years and cost $4,700,000.00. Over the three-year period, the MSPA's match will be $2,350,000.00 with some of those funds provided as in-kind services. To date, the MSPA has contributed $1,150,000.00.
 
Subject:
8.B. (JB) APPROVAL TO REJECT PROPOSALS RECEIVED FOR CONSTRUCTION MATERIALS TESTING
 
Description:
This item seeks board approval to reject proposals received for Construction Materials Testing in April 2024. MSPA received three proposals from geotechnical engineering firms operating materials testing labs. Staff recommends rejecting the proposals and advertising an RFQ for Geotechnical Engineering and Materials Testing Services.
 
Subject:
9. NEW BUSINESS
 
Subject:
9.A. (EL) APPROVAL OF RESOLUTION NO. 24-06 AUTHORIZING THE MSPA TO ALLOCATE AND EXPEND MATCHING FUNDS FOR THE EXCLUSIVE USE OF PROJECTS BEING PURSUED AND APPLIED FOR BY THE MSPA UNDER THE EPA CLEAN PORTS GRANT PROGRAMS
 
Description:
MSPA staff is seeking Board authorization to allocate and ultimately expend matching funds for the U.S. Environmental Protection Agency's Zero-Emission Technology Deployment Competition ("ZETD"). The total cost of the ZETD project is estimated to be $65,472,689.00.  The MSPA's proposed match for this project would be $1,950,190.50.  Collaborating entities will be providing matching funds in the amount of $4,597,078.40.
 
Subject:
9.B. (JB) APPROVAL TO ADVERTISE A REQUEST FOR QUALIFICATIONS FOR GEOTECHNICAL ENGINEERING AND CONSTRUCTION MATERIALS TESTING SERVICES
 
Description:
This item seeks board approval to advertise for qualifications for Geotechnical Engineering and Construction Materials Testing Services.
 
Subject:
10. ENGINEERING UPDATE
Subject:
11. OPERATIONS REPORT
Subject:
12. EXECUTIVE DIRECTOR'S REPORT
Subject:
13. GENERAL COUNSEL'S REPORT
Subject:
14. MDA COMMENTS
Subject:
15. COMMISSIONERS' COMMENTS
Subject:
16. EXECUTIVE SESSION - LEGAL MATTER

Web Viewer