skip to main content
Meeting Agenda
1. CALL TO ORDER/QUORUM
2. PLEDGE OF ALLEGIANCE
3. INVOCATION
4. ROTATION OF OFFICERS:

          PRESIDENT - VACANT
          VICE-PRESIDENT - JOHN RESTER
          SECRETARY - COWLES SYMMES
          TREASURER - MARK LOUGHMAN
          COMMISSIONER - ROBERT J. KNESAL

 
5. PUBLIC COMMENTS
6. MEETING MINUTES
7. APPROVAL OF TRAVEL
 
8. FINANCIAL REPORT 
 
8.A. DISBURSEMENTS
8.B. LICENSES
8.C. PROGRESS PAYMENTS
 
8.C.1. ANDERCORP, LLC / 22-EN-05

SHED 53 - OCEAN AERO IMPROVEMENTS - $ 121,130.76

 
8.C.2. BALCH & BINGHAM, LLP / 18-FD-04

FILL PERMIT CHALLENGE - $ 5,522.50
GENERAL LEGAL SERVICES - $ 4,760.12
WHARTON SMITH - $ 9,635.00
YILPORT LITIGATION - $ 64,955.22

TOTAL BALCH & BINGHAM - $ 84,872.84

 
8.C.3. BENECORP, INC. / 22-EN-06

SHED 50 ROLL-UP DOORS (FEMA) - $ 250,353.51

 
8.C.4. CONTINENTAL RAILS, INC. / 23-EN-02

EAST PIER RAIL REPAIRS - $ 103,547.15

 
8.C.5. DIGITAL ENGINEERING / 17-EN-04

HURRICANE ZETA SHED 50 ROLL-UP DOORS - TASK 14 - $ 524.00
HURR ZETA ARMORING STONE/EROSION REPAIRS - TASK 20 - $ 15,838.25
HURRICANE ZETA SHED 50 REPAIRS - TASK 21 - $ 8,499.50
10 YEAR MAINTENANCE DREDGING PERMIT - TASK 24 - $ 628.00
EAST PIER RAIL REPAIRS - TASK 25 - $ 4,225.50

TOTAL DIGITAL ENGINEERING - $ 29,715.25

 
8.C.6. DREDGING PROFESSOR, LLC / 23-EN-03

DEEPENING & WIDENING CONSULTING - $ 780.00

 
8.C.7. MP DESIGN GROUP / 22-EN-02

ACCESS ROAD PROJECT (MARAD) - $ 7,936.29

 
8.C.8. MP DESIGN GROUP / 23-EN-01

GENERAL ENGINEERING - WORK ORDER 1 - $ 8,033.75
REEFER PLUG ELEVATION (FEMA) - WO 2 - $ 14,190.00

TOTAL MP DESIGN GROUP - $ 22,223.75

 
8.C.9. WSP / 22-EN-04

STRATEGIC MASTER PLAN - $ 26,283.00

 
8.D. REQUESTS FOR CASH
 
8.D.1. RESTORATION AGREEMENT RFC #338

CH2M HILL - $ 34,220.80
ELEY GUILD HARDY - $ 12,992.00
WHARTON SMITH - $ 276,341.25

TOTAL REQUEST FOR CASH #338 - $ 323,554.05 AS "OTHER FUNDING" SOURCE - MSPA



 
9. OLD BUSINESS
 
9.A. (JB)  APPROVAL OF MODIFICATION NO. 2 TO WORK ORDER NO. 22 WITH DIGITAL ENGINEERING UNDER CONTRACT NO. 17-EN-04
 
9.B. (JB)  APPROVAL OF MODIFICATION NO. 1 TO WORK ORDER NO. 26 WITH DIGITAL ENGINEERING UNDER CONTRACT NO. 17-EN-04
 
9.C. (JB)  APPROVAL OF MODIFICATION NO. 3 TO CONTRACT NO. 17-EN-04 WITH DIGITAL ENGINEERING 
 
9.D. (JB)  APPROVAL OF CHANGE ORDER NO. 1 WITH BENECORP, INC. UNDER CONTRACT NO. 22-EN-06
 
10. NEW BUSINESS
 
10.A. (MW)  APPROVAL OF A PILOT RATE INCREASE
 
11. ENGINEERING UPDATE
12. OPERATIONS REPORT
13. EXECUTIVE DIRECTOR'S REPORT
14. GENERAL COUNSEL'S REPORT
15. MDA COMMENTS
16. COMMISSIONERS' COMMENTS
17. EXECUTIVE SESSION - LEGAL AND PERSONNEL MATTERS
Agenda Item Details Reload Your Meeting
Meeting: December 20, 2022 at 9:00 AM - Regular Meeting
Subject:
1. CALL TO ORDER/QUORUM
Subject:
2. PLEDGE OF ALLEGIANCE
Subject:
3. INVOCATION
Subject:
4. ROTATION OF OFFICERS:

          PRESIDENT - VACANT
          VICE-PRESIDENT - JOHN RESTER
          SECRETARY - COWLES SYMMES
          TREASURER - MARK LOUGHMAN
          COMMISSIONER - ROBERT J. KNESAL

 
Subject:
5. PUBLIC COMMENTS
Subject:
6. MEETING MINUTES
Subject:
7. APPROVAL OF TRAVEL
 
Subject:
8. FINANCIAL REPORT 
 
Subject:
8.A. DISBURSEMENTS
Subject:
8.B. LICENSES
Subject:
8.C. PROGRESS PAYMENTS
 
Subject:
8.C.1. ANDERCORP, LLC / 22-EN-05

SHED 53 - OCEAN AERO IMPROVEMENTS - $ 121,130.76

 
Subject:
8.C.2. BALCH & BINGHAM, LLP / 18-FD-04

FILL PERMIT CHALLENGE - $ 5,522.50
GENERAL LEGAL SERVICES - $ 4,760.12
WHARTON SMITH - $ 9,635.00
YILPORT LITIGATION - $ 64,955.22

TOTAL BALCH & BINGHAM - $ 84,872.84

 
Subject:
8.C.3. BENECORP, INC. / 22-EN-06

SHED 50 ROLL-UP DOORS (FEMA) - $ 250,353.51

 
Subject:
8.C.4. CONTINENTAL RAILS, INC. / 23-EN-02

EAST PIER RAIL REPAIRS - $ 103,547.15

 
Subject:
8.C.5. DIGITAL ENGINEERING / 17-EN-04

HURRICANE ZETA SHED 50 ROLL-UP DOORS - TASK 14 - $ 524.00
HURR ZETA ARMORING STONE/EROSION REPAIRS - TASK 20 - $ 15,838.25
HURRICANE ZETA SHED 50 REPAIRS - TASK 21 - $ 8,499.50
10 YEAR MAINTENANCE DREDGING PERMIT - TASK 24 - $ 628.00
EAST PIER RAIL REPAIRS - TASK 25 - $ 4,225.50

TOTAL DIGITAL ENGINEERING - $ 29,715.25

 
Subject:
8.C.6. DREDGING PROFESSOR, LLC / 23-EN-03

DEEPENING & WIDENING CONSULTING - $ 780.00

 
Subject:
8.C.7. MP DESIGN GROUP / 22-EN-02

ACCESS ROAD PROJECT (MARAD) - $ 7,936.29

 
Subject:
8.C.8. MP DESIGN GROUP / 23-EN-01

GENERAL ENGINEERING - WORK ORDER 1 - $ 8,033.75
REEFER PLUG ELEVATION (FEMA) - WO 2 - $ 14,190.00

TOTAL MP DESIGN GROUP - $ 22,223.75

 
Subject:
8.C.9. WSP / 22-EN-04

STRATEGIC MASTER PLAN - $ 26,283.00

 
Subject:
8.D. REQUESTS FOR CASH
 
Subject:
8.D.1. RESTORATION AGREEMENT RFC #338

CH2M HILL - $ 34,220.80
ELEY GUILD HARDY - $ 12,992.00
WHARTON SMITH - $ 276,341.25

TOTAL REQUEST FOR CASH #338 - $ 323,554.05 AS "OTHER FUNDING" SOURCE - MSPA



 
Subject:
9. OLD BUSINESS
 
Subject:
9.A. (JB)  APPROVAL OF MODIFICATION NO. 2 TO WORK ORDER NO. 22 WITH DIGITAL ENGINEERING UNDER CONTRACT NO. 17-EN-04
 
Description:
Provided for professional engineering services and architectural services related to the conceptual and preliminary designs associated with some proposed modifications to East Pier Shed 53 for a potential new tenant. The de-obligated amount for this modification is $13,464.50.
 
Subject:
9.B. (JB)  APPROVAL OF MODIFICATION NO. 1 TO WORK ORDER NO. 26 WITH DIGITAL ENGINEERING UNDER CONTRACT NO. 17-EN-04
 
Description:
Provided for professional engineering services related to obtaining a Wetlands Permit for the "Cotton Compress Site Fencing" project. The de-obligated amount for this modification is $7,844.00.
 
Subject:
9.C. (JB)  APPROVAL OF MODIFICATION NO. 3 TO CONTRACT NO. 17-EN-04 WITH DIGITAL ENGINEERING 
 
Description:
This agenda item seeks Board approval of a proposed Modification to extend Digital Engineering's Professional Engineering Services Agreement for an additional twelve months so they can complete on-going Work Orders. All work will be billed in accordance with the approved fee schedule of the master service agreement.  It is recommended that Modification No. 3 be approved as submitted.
 
Subject:
9.D. (JB)  APPROVAL OF CHANGE ORDER NO. 1 WITH BENECORP, INC. UNDER CONTRACT NO. 22-EN-06
 
Description:
This agenda item seeks Board approval of a proposed Change Order No. 1 to the Hurricane Zeta Shed 50 Overhead Door Repairs for work relating to the hurricane damage and replacement of overhead doors in Shed 50. We are requesting additional days be added to the contract due to material delays. This change order will add 65 days to the contract. 
It is recommended that Change Order No. 1 be approved as submitted.

 
Subject:
10. NEW BUSINESS
 
Subject:
10.A. (MW)  APPROVAL OF A PILOT RATE INCREASE
 
Description:
In accordance with procedures approved on December 20, 2018, a Pilot rate increase of 3.0% is being requested with an effective date of January 1, 2023.  Port Staff recommends approval.
 
Subject:
11. ENGINEERING UPDATE
Subject:
12. OPERATIONS REPORT
Subject:
13. EXECUTIVE DIRECTOR'S REPORT
Subject:
14. GENERAL COUNSEL'S REPORT
Subject:
15. MDA COMMENTS
Subject:
16. COMMISSIONERS' COMMENTS
Subject:
17. EXECUTIVE SESSION - LEGAL AND PERSONNEL MATTERS

Web Viewer