Meeting Agenda
|
---|
1. CALL TO ORDER/QUORUM
|
2. PLEDGE OF ALLEGIANCE
|
3. INVOCATION - CARLOS BELL
|
4. PUBLIC COMMENTS
|
5. MEETING MINUTES
|
6. APPROVAL OF TRAVEL
|
7. FINANCIAL REPORT - DEEDEE WOOD
|
7.A. DISBURSEMENTS
|
7.B. PROGRESS PAYMENTS
|
7.B.1. BALCH & BINGHAM,LLP/18-FD-04
|
7.B.2. BROWN, MITCHELL & ALEXANDER, INC./13-EN-02
|
7.B.3. DIGITAL ENGINEERING/017-EN-04
|
7.C. REQUESTS FOR CASH
|
7.C.1. RESTORATION AGREEMENT RFC #214
|
7.C.2. RESTORATION AGREEMENT RFC #215
|
7.C.3. RESTORATION AGREEMENT RFC #216
|
7.C.4. RESTORATION AGREEMENT RFC #217
|
7.C.5. RESTORATION AGREEMENT #218
|
8. OLD BUSINESS
|
8.A. (NF) APPROVAL OF DE-OBLIGATED AMOUNTS IN ORDER TO CLOSE OUT COMPLETED AND ACCEPTED WORK:
QES, INC./010-HUD-003 - AMENDMENT 2 TO TASK ORDER 20 QES, INC./010-HUD-003 - AMENDMENT 1 TO TASK ORDER 25 |
8.B. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 27 WITH THOMPSON ENGINEERING UNDER CONTRACT NO. 010-HUD-002
|
8.C. (NF) APPROVAL OF AMENDMENT 9 UNDER CONTRACT NO. 010-HUD-003 WITH QES, INC.
|
8.D. (NF) APPROVAL OF AMENDMENT 9 WITH VOLKERT, INC. UNDER CONTRACT NO. 010-HUD-007
|
8.E. (NF) APPROVAL OF AMENDMENT 6 TO ATWELL & GENT UNDER CONTRACT NO. 010-HUD-013
|
8.F. (NF) APPROVAL OF AMENDMENTS TO ADD TIME TO CONTINUE SERVICES FOR THE WEST PIER SITEWORK AND INFRASTRUCTURE PHASE 3 ACTIVITIES THROUGH THE 10/31/18 COMPLETION DATE:
010-HUD-001/NEEL SCHAFFER - AMENDMENT 3 TO TASK ORDER 49 - ADDS 123 DAYS 010-HUD-002/QES, INC. - AMENDMENT 2 TO TASK ORDER 22 - ADDS 153 DAYS |
8.G. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 15 WITH VOLKERT, INC. UNDER CONTRACT NO. 010-HUD-007
|
8.H. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 16 WITH VOLKERT, INC. UNDER CONTRACT NO. 010-HUD-007
|
8.I. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 22 WITH ATWELL & GENT UNDER CONTRACT NO. 010-HUD-013
|
8.J. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 7 WITH ELEY GUILD HARDY UNDER CONTRACT NO. 016/HUD-031
|
8.K. (NF) APPROVAL OF CHANGE ORDER 4 WITH J.O. COLLINS UNDER CONTRACT NO. 017-HUD-042
|
8.L. (NF) AUTHORIZATION TO AWARD THE MITIGATION PROPERTY PROJECT
|
8.M. (MW) AUTHORIZATION TO ADD FUNDING (VIA GENERAL COUNSEL) FOR PHASE II TASKS PERFORMED BY MSPA'S GENERAL ENGINEERING FIRM RE: POTENTIAL PROPERTY PURCHASE
|
9. PORT RESTORATION UPDATE - NICK FOTO
|
10. OPERATIONS/DEPUTY DIRECTOR'S REPORT - MATTHEW WYPYSKI
|
11. GENERAL COUNSEL COMMENTS
|
12. MDA COMMENTS
|
13. COMMISSIONER COMMENTS
|
14. EXECUTIVE SESSION - LEGAL MATTERS AND PERSONNEL MATTERS
|
15. PRESENTATIONS - RFP RESPONSES (2) FOR INVESTMENT SERVICES
|
16. ADJOURNMENT
|
Agenda Item Details
Reload Your Meeting
|
||
---|---|---|
Meeting: | May 17, 2018 at 1:00 PM - Regular Commission Meeting | |
Subject: |
1. CALL TO ORDER/QUORUM
|
|
Subject: |
2. PLEDGE OF ALLEGIANCE
|
|
Subject: |
3. INVOCATION - CARLOS BELL
|
|
Subject: |
4. PUBLIC COMMENTS
|
|
Subject: |
5. MEETING MINUTES
|
|
Subject: |
6. APPROVAL OF TRAVEL
|
|
Subject: |
7. FINANCIAL REPORT - DEEDEE WOOD
|
|
Subject: |
7.A. DISBURSEMENTS
|
|
Subject: |
7.B. PROGRESS PAYMENTS
|
|
Subject: |
7.B.1. BALCH & BINGHAM,LLP/18-FD-04
|
|
Description:
GENERAL LEGAL SERVICES - $ 7,140.00
SOUTHERN INDUSTRIAL CONTRACTORS - $ 46,199.43 RESTORATION ACTIVITIES – $ 23,098.70 LAND ACQUISITION - $ 47,282.59 MITIGATION PROPERTY - $ 5,649.20 TOTAL BALCH & BINGHAM - $ 129,369.92 |
||
Subject: |
7.B.2. BROWN, MITCHELL & ALEXANDER, INC./13-EN-02
|
|
Description:
CHEMOURS ENHANCEMENT PROJECT – TASK 5 - $ 4,772.00
EAST PIER WHARF IMPROVEMENTS - TASK 10 - $ 17,115.25 TOTAL BMA - $ 21,887.25 |
||
Subject: |
7.B.3. DIGITAL ENGINEERING/017-EN-04
|
|
Description:
GENERAL ENGINEERING – TASK 1 - $ 22,732.00
EAST PIER FENDER PROJECT – TASK 2 - $ 1,224.00 NORTH PORT DEVELOPMENT TASK 4 - $ 73,947.00 DOD STORAGE FACILITY TASK 5 - $ 84,032.50 TOTAL DIGITAL ENGINEERING - $ 181,935.50 |
||
Subject: |
7.C. REQUESTS FOR CASH
|
|
Subject: |
7.C.1. RESTORATION AGREEMENT RFC #214
|
|
Description:
CH2M HILL - $ 201,307.69
J.O. COLLINS - $ 16,611.72 MSPA - $ 60,105.59 THOMPSON ENGINEERING - $ 3,906.62 TOTAL REQUEST FOR CASH #214 – $ 281,931.62 |
||
Subject: |
7.C.2. RESTORATION AGREEMENT RFC #215
|
|
Description:
NECAISE BROTHERS - $ 4,906,809.88
TOTAL REQUEST FOR CASH #215 – $ 4,906,809.88 |
||
Subject: |
7.C.3. RESTORATION AGREEMENT RFC #216
|
|
Description:
NECAISE BROTHERS - $ 2,698,204.97
TOTAL REQUEST FOR CASH #216 – $ 2,698,204.97 |
||
Subject: |
7.C.4. RESTORATION AGREEMENT RFC #217
|
|
Description:
TRAVELERS AS SURETY - $ 861,219.91
|
||
Subject: |
7.C.5. RESTORATION AGREEMENT #218
|
|
Description:
ZPMC - $ 4,638,446.47
TOTAL REQUEST FOR CASH #218 – $ 4,638,446.47 |
||
Subject: |
8. OLD BUSINESS
|
|
Subject: |
8.A. (NF) APPROVAL OF DE-OBLIGATED AMOUNTS IN ORDER TO CLOSE OUT COMPLETED AND ACCEPTED WORK:
QES, INC./010-HUD-003 - AMENDMENT 2 TO TASK ORDER 20 QES, INC./010-HUD-003 - AMENDMENT 1 TO TASK ORDER 25 |
|
Subject: |
8.B. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 27 WITH THOMPSON ENGINEERING UNDER CONTRACT NO. 010-HUD-002
|
|
Subject: |
8.C. (NF) APPROVAL OF AMENDMENT 9 UNDER CONTRACT NO. 010-HUD-003 WITH QES, INC.
|
|
Subject: |
8.D. (NF) APPROVAL OF AMENDMENT 9 WITH VOLKERT, INC. UNDER CONTRACT NO. 010-HUD-007
|
|
Subject: |
8.E. (NF) APPROVAL OF AMENDMENT 6 TO ATWELL & GENT UNDER CONTRACT NO. 010-HUD-013
|
|
Subject: |
8.F. (NF) APPROVAL OF AMENDMENTS TO ADD TIME TO CONTINUE SERVICES FOR THE WEST PIER SITEWORK AND INFRASTRUCTURE PHASE 3 ACTIVITIES THROUGH THE 10/31/18 COMPLETION DATE:
010-HUD-001/NEEL SCHAFFER - AMENDMENT 3 TO TASK ORDER 49 - ADDS 123 DAYS 010-HUD-002/QES, INC. - AMENDMENT 2 TO TASK ORDER 22 - ADDS 153 DAYS |
|
Subject: |
8.G. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 15 WITH VOLKERT, INC. UNDER CONTRACT NO. 010-HUD-007
|
|
Subject: |
8.H. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 16 WITH VOLKERT, INC. UNDER CONTRACT NO. 010-HUD-007
|
|
Subject: |
8.I. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 22 WITH ATWELL & GENT UNDER CONTRACT NO. 010-HUD-013
|
|
Subject: |
8.J. (NF) APPROVAL OF AMENDMENT 1 TO TASK ORDER 7 WITH ELEY GUILD HARDY UNDER CONTRACT NO. 016/HUD-031
|
|
Subject: |
8.K. (NF) APPROVAL OF CHANGE ORDER 4 WITH J.O. COLLINS UNDER CONTRACT NO. 017-HUD-042
|
|
Subject: |
8.L. (NF) AUTHORIZATION TO AWARD THE MITIGATION PROPERTY PROJECT
|
|
Subject: |
8.M. (MW) AUTHORIZATION TO ADD FUNDING (VIA GENERAL COUNSEL) FOR PHASE II TASKS PERFORMED BY MSPA'S GENERAL ENGINEERING FIRM RE: POTENTIAL PROPERTY PURCHASE
|
|
Subject: |
9. PORT RESTORATION UPDATE - NICK FOTO
|
|
Subject: |
10. OPERATIONS/DEPUTY DIRECTOR'S REPORT - MATTHEW WYPYSKI
|
|
Subject: |
11. GENERAL COUNSEL COMMENTS
|
|
Subject: |
12. MDA COMMENTS
|
|
Subject: |
13. COMMISSIONER COMMENTS
|
|
Subject: |
14. EXECUTIVE SESSION - LEGAL MATTERS AND PERSONNEL MATTERS
|
|
Subject: |
15. PRESENTATIONS - RFP RESPONSES (2) FOR INVESTMENT SERVICES
|
|
Subject: |
16. ADJOURNMENT
|