skip to main content
Meeting Agenda
1. CALL TO ORDER/QUORUM
2. PLEDGE OF ALLEGIANCE
3. PUBLIC COMMENTS
4. APPROVAL OF MINUTES
5. APPROVAL OF TRAVEL
6. FINANCIAL REPORT - MARY BOURDIN
6.A. DISBURSEMENTS
6.B. LICENSES
6.C. PROGRESS PAYMENTS
6.C.1. BALCH & BINGHAM,LLP/14-FD-08
6.C.2. BROWN, MITCHELL & ALEXANDER, INC./13-EN-02
6.C.3. CONTINENTAL CONSTRUCTION CO., INC/15-EN-02
6.C.4. DOLEAC ELECTRIC CO.,INC./15-EN-08
6.C.5. G.A. WEST & CO., INC./15-EN-03
6.C.6. QES, INC./13-EN-03
6.C.7. YATES ANDERSON JOINT VENTURE/14-EN-07
6.C.8. ZPMC, LTD/ 15-EN-07
6.D. REQUESTS FOR CASH
6.D.1. RESTORATION AGREEMENT RFC #120
6.D.2. RESTORATION AGREEMENT RFC #121
6.D.3. RESTORATION AGREEMENT RFC #122
6.E. FOR SEPARATE APPROVAL
6.E.1. FROM RESTORATION AGREEMENT REQUEST #120:

CH2M HILL - $208,585.61
6.E.2. FROM RESTORATION AGREEMENT REQUEST #120

ELEY, GUILD, HARDY - $ 44,208.50

TOTAL REQUEST FOR CASH  #120 - $ 1,612,072.18
7. OLD BUSINESS
7.A. (NF)  APPROVAL OF AMENDMENT NO. 1 TO CONTRACT NO. 013-HUD-017 WITH RFB, LLC  
7.B. (JW)  AUTHORIZATION TO ADVERTISE FOR BID THE BERTH 7 FENDER REPLACEMENT PROJECT
7.C. (JW)  AUTHORIZATION TO ADVERTISE FOR BID THE BERTH 7 DREDGING PROJECT
7.D. (NF)  APPROVAL OF AMENDMENT NO. 4 TO TASK ORDER NO. 21 WITH NEEL-SCHAFFER, INC. UNDER CONTRACT NO. 010-HUD-001
7.E. (NF)  APPROVAL OF AMENDMENT NO. 7 TO TASK ORDER NO. 22 WITH NEEL-SCHAFFER, INC. UNDER CONTRACT NO. 010-HUD-001
7.F. (NF)  APPROVAL OF AMENDMENT NO. 2 TO TASK ORDER NO. 18 WITH THOMPSON ENGINEERING UNDER CONTRACT NO. 010-HUD-002
7.G. (NF)  APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 6 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
7.H. (NF)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 10 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
7.I. (JW)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 12 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
7.J. (JW)  APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 9 WITH YAJV UNDER CONTRACT NO. 010-HUD-006
7.K. (JW)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 17 WITH YAJV UNDER CONTRACT NO. 010-HUD-006
7.L. (NF)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 12 WITH VOLKERT,INC. UNDER CONTRACT NO. 010-HUD-007
7.M. (NF)  APPROVAL OF AMENDMENT NO. 2 WITH TASK ORDER NO. 13 WITH ANCHOR QEA, LLC UNDER CONTRACT NO. 010-HUD-011
7.N. (NF)  APPROVAL OF AMENDMENT NO. 4 TO TASK ORDER NO. 20 WITH ANCHOR QEA, LLC UNDER CONTRACT NO. 010-HUD-011
7.O. (JW)  APPROVAL OF AMENDMENT NO. 5 TO TASK ORDER NO. 2 WITH ATWELL & GENT, P.A. UNDER CONTRACT NO. 010-HUD-013
7.P. (NF)  APPROVAL OF CHANGE ORDER NO. 2 TO SOUTHERN INDUSTRIAL CONTRACTORS UNDER CONTRACT NO. 015-HUD-025
7.Q. (NF)  APPROVAL OF CHANGE ORDER NO. 11 TO L&A CONTRACTING UNDER CONTRACT NO. 013-HUD-018
7.R. (NF)  APPROVAL OF CHANGE ORDER NO. 7 TO NECAISE BROTHERS CONSTRUCTION UNDER CONTRACT NO. 015-HUD-026
7.S. (NF)  APPROVAL OF CHANGE ORDER NO. 4 TO DAN HENSARLING, INC. UNDER CONTRACT NO. 015-HUD-029
7.T. (MW)  APPROVAL OF AMENDMENT NO. 2 TO THE TERMINAL OPERATING AGREEMENT AND SPACE ASSIGNMENT WITH CROWLEY LATIN AMERICA SERVICES, INC.
8. NEW BUSINESS
8.A. (JD)  APPROVAL OF RESOLUTION NO. 16-03 REGARDING THE LEASEHOLD DEED OF TRUST RELATIVE TO THE MCDERMOTT, INC. LEASE
9. PORT RESTORATION UPDATE  - NICK FOTO
10. OPERATIONS REPORT - MATTHEW WYPYSKI
11. STATUS REPORT ON THE ENVIRONMENTAL IMPACT STATEMENT - ELIZABETH CALVIT, CH2MHILL
12. EXECUTIVE DIRECTOR’S REPORT - JONATHAN DANIELS
13. GENERAL COUNSEL’S COMMENTS
14. MDA COMMENTS
15. COMMISSIONER COMMENTS
16.  EXECUTIVE SESSION - LEGAL MATTERS (LITIGATION)
17. ADJOURNMENT
Agenda Item Details Reload Your Meeting
Meeting: April 20, 2016 at 8:30 AM - Regular Commission Meeting
Subject:
1. CALL TO ORDER/QUORUM
Subject:
2. PLEDGE OF ALLEGIANCE
Subject:
3. PUBLIC COMMENTS
Subject:
4. APPROVAL OF MINUTES
Subject:
5. APPROVAL OF TRAVEL
Subject:
6. FINANCIAL REPORT - MARY BOURDIN
Subject:
6.A. DISBURSEMENTS
Subject:
6.B. LICENSES
Subject:
6.C. PROGRESS PAYMENTS
Subject:
6.C.1. BALCH & BINGHAM,LLP/14-FD-08
Description:
GENERAL LEGAL SERVICES - $ 21,855.68
RESTORATION ACTIVITIES - $ 6,752.03
SOUTHERN INDUSTRIAL CONTRACTORS - $ 2,543.75
W C FORE TRUCKING APPEAL - $ 21,792.00

TOTAL BALCH & BINGHAM - $ 52,943.46
Subject:
6.C.2. BROWN, MITCHELL & ALEXANDER, INC./13-EN-02
Description:
GENERAL ENGINEERING - TASK 1 - $ 2,872.50
BULK HANDLING FACILITY – TASK 5 - $ 85,751.44
BERTH 7 DREDGE - TASK 6 - $ 1,378.00

TOTAL BMA - $ 90,001.94
Subject:
6.C.3. CONTINENTAL CONSTRUCTION CO., INC/15-EN-02
Description:
BULK HANDLING FACILITY  - SILO PACKAGE – $316,207.50
Subject:
6.C.4. DOLEAC ELECTRIC CO.,INC./15-EN-08
Description:
BULK HANDLING FACILITY - $91,867.85
Subject:
6.C.5. G.A. WEST & CO., INC./15-EN-03
Description:
BULK HANDLING FACILITY  - CONVEYOR PACKAGE – $1,860,394.84
Subject:
6.C.6. QES, INC./13-EN-03
Description:
BULK HANDLING FACILITY - MATERIALS TESTING - $ 4,254.00
Subject:
6.C.7. YATES ANDERSON JOINT VENTURE/14-EN-07
Description:
BULK HANDLING FACILITY CM - $231,945.91
Subject:
6.C.8. ZPMC, LTD/ 15-EN-07
Description:
TRAVELING HOPPER - $ 192,000.00
Subject:
6.D. REQUESTS FOR CASH
Subject:
6.D.1. RESTORATION AGREEMENT RFC #120
Description:

THOMPSON ENGINEERING - $ 16,676.16
NEEL-SCHAFFER - $ 176,326.44
ATWELL & GENT - $ 16,254.84        
ANCHOR QEA - $ 39,185.26
ATKINS - $ 33,986.81
QES - $ 68,814.41
MSPA - $ 118,739.34
MICHAEL BAKER  - $ 9,736.43
CDM - $ 79,684.83
RFB, INC - $ 3,846.25
YATES ANDERSON JOINT VENTURE - $ 495,092.00
DAN HENSARLING - $ 239,016.20
WHARTON SMITH - $ 61,919.10

RESTORATION AGREEMENT RFC #116 SUBTOTAL - $ 1,359,278.07
Subject:
6.D.2. RESTORATION AGREEMENT RFC #121
Description:

NECAISE BROTHERS - $ 4,978,790.30
Subject:
6.D.3. RESTORATION AGREEMENT RFC #122
Description:

L&A CONTRACTORS - $ 1,008,412.25
RFB, LLC - $ 3,315.00

TOTAL REQUEST FOR CASH  #122 - $ 1,011,727.25
Subject:
6.E. FOR SEPARATE APPROVAL
Subject:
6.E.1. FROM RESTORATION AGREEMENT REQUEST #120:

CH2M HILL - $208,585.61
Subject:
6.E.2. FROM RESTORATION AGREEMENT REQUEST #120

ELEY, GUILD, HARDY - $ 44,208.50

TOTAL REQUEST FOR CASH  #120 - $ 1,612,072.18
Subject:
7. OLD BUSINESS
Subject:
7.A. (NF)  APPROVAL OF AMENDMENT NO. 1 TO CONTRACT NO. 013-HUD-017 WITH RFB, LLC  
Subject:
7.B. (JW)  AUTHORIZATION TO ADVERTISE FOR BID THE BERTH 7 FENDER REPLACEMENT PROJECT
Subject:
7.C. (JW)  AUTHORIZATION TO ADVERTISE FOR BID THE BERTH 7 DREDGING PROJECT
Subject:
7.D. (NF)  APPROVAL OF AMENDMENT NO. 4 TO TASK ORDER NO. 21 WITH NEEL-SCHAFFER, INC. UNDER CONTRACT NO. 010-HUD-001
Subject:
7.E. (NF)  APPROVAL OF AMENDMENT NO. 7 TO TASK ORDER NO. 22 WITH NEEL-SCHAFFER, INC. UNDER CONTRACT NO. 010-HUD-001
Subject:
7.F. (NF)  APPROVAL OF AMENDMENT NO. 2 TO TASK ORDER NO. 18 WITH THOMPSON ENGINEERING UNDER CONTRACT NO. 010-HUD-002
Subject:
7.G. (NF)  APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 6 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
Subject:
7.H. (NF)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 10 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
Subject:
7.I. (JW)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 12 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
Subject:
7.J. (JW)  APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 9 WITH YAJV UNDER CONTRACT NO. 010-HUD-006
Subject:
7.K. (JW)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 17 WITH YAJV UNDER CONTRACT NO. 010-HUD-006
Subject:
7.L. (NF)  APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 12 WITH VOLKERT,INC. UNDER CONTRACT NO. 010-HUD-007
Subject:
7.M. (NF)  APPROVAL OF AMENDMENT NO. 2 WITH TASK ORDER NO. 13 WITH ANCHOR QEA, LLC UNDER CONTRACT NO. 010-HUD-011
Subject:
7.N. (NF)  APPROVAL OF AMENDMENT NO. 4 TO TASK ORDER NO. 20 WITH ANCHOR QEA, LLC UNDER CONTRACT NO. 010-HUD-011
Subject:
7.O. (JW)  APPROVAL OF AMENDMENT NO. 5 TO TASK ORDER NO. 2 WITH ATWELL & GENT, P.A. UNDER CONTRACT NO. 010-HUD-013
Subject:
7.P. (NF)  APPROVAL OF CHANGE ORDER NO. 2 TO SOUTHERN INDUSTRIAL CONTRACTORS UNDER CONTRACT NO. 015-HUD-025
Subject:
7.Q. (NF)  APPROVAL OF CHANGE ORDER NO. 11 TO L&A CONTRACTING UNDER CONTRACT NO. 013-HUD-018
Subject:
7.R. (NF)  APPROVAL OF CHANGE ORDER NO. 7 TO NECAISE BROTHERS CONSTRUCTION UNDER CONTRACT NO. 015-HUD-026
Subject:
7.S. (NF)  APPROVAL OF CHANGE ORDER NO. 4 TO DAN HENSARLING, INC. UNDER CONTRACT NO. 015-HUD-029
Subject:
7.T. (MW)  APPROVAL OF AMENDMENT NO. 2 TO THE TERMINAL OPERATING AGREEMENT AND SPACE ASSIGNMENT WITH CROWLEY LATIN AMERICA SERVICES, INC.
Subject:
8. NEW BUSINESS
Subject:
8.A. (JD)  APPROVAL OF RESOLUTION NO. 16-03 REGARDING THE LEASEHOLD DEED OF TRUST RELATIVE TO THE MCDERMOTT, INC. LEASE
Subject:
9. PORT RESTORATION UPDATE  - NICK FOTO
Subject:
10. OPERATIONS REPORT - MATTHEW WYPYSKI
Subject:
11. STATUS REPORT ON THE ENVIRONMENTAL IMPACT STATEMENT - ELIZABETH CALVIT, CH2MHILL
Subject:
12. EXECUTIVE DIRECTOR’S REPORT - JONATHAN DANIELS
Subject:
13. GENERAL COUNSEL’S COMMENTS
Subject:
14. MDA COMMENTS
Subject:
15. COMMISSIONER COMMENTS
Subject:
16.  EXECUTIVE SESSION - LEGAL MATTERS (LITIGATION)
Subject:
17. ADJOURNMENT

Web Viewer