Meeting Agenda
I. Call to Order
II. Discussion Items
II.A. Discussion of Summer 2023 Work
II.A.1. MacArthur Phase 2 - HVAC
II.A.2. Sullivan Plumbing
II.A.3. Eisenhower Projector & Whiteboard Replacements
II.A.4. Eisenhower Fencing
II.B. Safety & Security Signage
II.C. Window, Siding and Door Replacements - Update
II.D. Building Tour and Certification of the Facilities
III. Old Business
IV. New Business
V. Adjournment
Agenda Item Details Reload Your Meeting
Meeting: August 1, 2023 at 10:00 AM - District 23 Buildings & Sites Committee Meeting
Subject:
I. Call to Order
Subject:
II. Discussion Items
Subject:
II.A. Discussion of Summer 2023 Work
Description:
Amy will share an update on each of the Summer 2023 Projects
Subject:
II.A.1. MacArthur Phase 2 - HVAC
Description:
Amy will update the committee on the HVAC work.  A log of deductions against the allowance amount has been attached.  Project is on track for substantial completion by August 7, 2023 with commissioning to take place the week of 8/7/2023.
Attachments:
Subject:
II.A.2. Sullivan Plumbing
Description:
The tile demo was completed this week and the vapor barrier was applied on 7/28. Following some unanticipated tile delays, we have selected an alternate tile for the classroom.  Temporary carpet tile will be laid in the hallway until mid-late August.  All classrooms will be cleaned and ready for teacher and student use by 8/7.
Subject:
II.A.3. Eisenhower Projector & Whiteboard Replacements
Description:
Following board demo and recycling, all walls have been restored and painted.  New boards have been hung.  projector wiring has been completed and final projectors are being mounted.  All rooms will have Apple TV's completed by the end of the week for staff use.
Subject:
II.A.4. Eisenhower Fencing
Description:
Fencing being installed at both locations Wednesday-Thursday next week.  Landscape clearing to take place this weekend.
Subject:
II.B. Safety & Security Signage
Description:
Amy will provide an update on building signage, including building visitor, AED and park/path signs.
Subject:
II.C. Window, Siding and Door Replacements - Update
Description:
Amy will share the updated calendar, project scope and budget with the committee.  Documents have been attached for review. 
Attachments:
Subject:
II.D. Building Tour and Certification of the Facilities
Description:
Following the meeting, all are welcome to walk the buildings to review this summer's work.
Subject:
III. Old Business
Subject:
IV. New Business
Subject:
V. Adjournment