6.B. LICENSES
6.C. PROGRESS PAYMENTS
 
6.C.1. BALCH & BINGHAM, LLP / 18-FD-04

          GENERAL LEGAL SERVICES - $ 58,644.50
          TRANSACTIONAL SERVICES  - $ 588.00
                    
          TOTAL BALCH & BINGHAM - $ 59,232.50

 
6.C.2. COVINGTON CIVIL AND ENVIRONMENTAL LLC / 23-EN-06
       
         GROUND WATER MONITOR GULFPORT FERTILIZER SITE - $ 7,002.81

 
6.C.3. HDR ENGINEERING, INC. / 24-EN-04
           
         
STRATEGIC MASTER PLAN - $ 4,087.00
 
6.C.4. MP DESIGN GROUP / 23-EN-01

          EAST PIER CONTAINMENT BERM - WORK ORDER 14 - $ 62,523.75
          RAIL TIE REPLACEMENT - WORK ORDER 18 - $ 1,055.00
          ANNUAL VISUAL INSPECTIONS - WORK ORDER 19 - $ 1,900.00
          REPAINT WP TENANT GATES - WORK ORDER 20 - $ 3,835.00
          UNDER WATER WHARF REPAIRS EAST PIER - WORK ORDER 21 - $ 11,169.80

          TOTAL MP DESIGN GROUP - $ 80,483.55

 
6.C.5. MP DESIGN GROUP / 27-EN-01

         
ENGINEERING SERVICES - WORK ORDER 1 - $ 1,200.00
         GRANT SUPPORT - WORK ORDER 2 - $ 720.00
         ELECTRICAL CHEMOURS MOBILE CRANE - WORK ORDER 3 - $ 19,847.50
         ADVANCED MARINE TECH FACILITY - WORK ORDER 4 - $ 30,546.55
         SHORELINE PROTECTION NORTH HARBOR - WORK ORDER 5 - $ 9,850.00
         BUSINESS DEVELOPMENT SUPPORT - WORK ORDER 6 - $ 1,337.50

         TOTAL MP DESIGN GROUP - $ 63,501.55

 
6.C.6. TWIN L CONSTRUCTION LLC / 26-EN-04

         
REPAINT WP TENANT GATES - $ 73,411.25

 
7. OLD BUSINESS
 
8. NEW BUSINESS
 
8.A. (BC) APPROVAL OF WORK ORDER NO. 8 FOR CONTRACT 27-EN-01
 
8.B. (BC) REQUEST APPROVAL TO ADVERTISE FOR BIDS
 
8.C. (SM) REQUEST AUTHORIZATION TO RETROFIT SHED 2 DOORS
 
9. ENGINEERING UPDATE
10. OPERATIONS REPORT
11. EXECUTIVE DIRECTOR'S REPORT
12. GENERAL COUNSEL'S REPORT
13. MDA COMMENTS
14. COMMISSIONERS' COMMENTS
15. EXECUTIVE SESSION - LEGAL, REAL ESTATE, AND PERSONNEL MATTER
Agenda Item Details Reload Your Meeting
Meeting: November 19, 2026 at 10:30 AM - Regular Meeting
Subject:
1. CALL TO ORDER/QUORUM
Subject:
2. PLEDGE OF ALLEGIANCE
Subject:
3. INVOCATION
Subject:
4. PUBLIC COMMENTS
Subject:
5. MEETING MINUTES
Subject:
6. FINANCIAL REPORT 
 
Subject:
6.A. DISBURSEMENTS
Subject:
6.B. LICENSES
Subject:
6.C. PROGRESS PAYMENTS
 
Subject:
6.C.1. BALCH & BINGHAM, LLP / 18-FD-04

          GENERAL LEGAL SERVICES - $ 58,644.50
          TRANSACTIONAL SERVICES  - $ 588.00
                    
          TOTAL BALCH & BINGHAM - $ 59,232.50

 
Subject:
6.C.2. COVINGTON CIVIL AND ENVIRONMENTAL LLC / 23-EN-06
       
         GROUND WATER MONITOR GULFPORT FERTILIZER SITE - $ 7,002.81

 
Subject:
6.C.3. HDR ENGINEERING, INC. / 24-EN-04
           
         
STRATEGIC MASTER PLAN - $ 4,087.00
 
Subject:
6.C.4. MP DESIGN GROUP / 23-EN-01

          EAST PIER CONTAINMENT BERM - WORK ORDER 14 - $ 62,523.75
          RAIL TIE REPLACEMENT - WORK ORDER 18 - $ 1,055.00
          ANNUAL VISUAL INSPECTIONS - WORK ORDER 19 - $ 1,900.00
          REPAINT WP TENANT GATES - WORK ORDER 20 - $ 3,835.00
          UNDER WATER WHARF REPAIRS EAST PIER - WORK ORDER 21 - $ 11,169.80

          TOTAL MP DESIGN GROUP - $ 80,483.55

 
Subject:
6.C.5. MP DESIGN GROUP / 27-EN-01

         
ENGINEERING SERVICES - WORK ORDER 1 - $ 1,200.00
         GRANT SUPPORT - WORK ORDER 2 - $ 720.00
         ELECTRICAL CHEMOURS MOBILE CRANE - WORK ORDER 3 - $ 19,847.50
         ADVANCED MARINE TECH FACILITY - WORK ORDER 4 - $ 30,546.55
         SHORELINE PROTECTION NORTH HARBOR - WORK ORDER 5 - $ 9,850.00
         BUSINESS DEVELOPMENT SUPPORT - WORK ORDER 6 - $ 1,337.50

         TOTAL MP DESIGN GROUP - $ 63,501.55

 
Subject:
6.C.6. TWIN L CONSTRUCTION LLC / 26-EN-04

         
REPAINT WP TENANT GATES - $ 73,411.25

 
Subject:
7. OLD BUSINESS
 
Subject:
8. NEW BUSINESS
 
Subject:
8.A. (BC) APPROVAL OF WORK ORDER NO. 8 FOR CONTRACT 27-EN-01
 
Description:
This agenda item seeks approval of MPs Work Order No. 8 in an amount not to exceed $422,035.00 for engineering design services, contract documents, and construction administration services for Intermodal Expansion and Enhancements Project under SMIF Grant 24-007.
 
Subject:
8.B. (BC) REQUEST APPROVAL TO ADVERTISE FOR BIDS
 
Description:
This item seeks Board approval to Advertise for Bids for the Shoreline Stabilization Improvement Project.
 
Subject:
8.C. (SM) REQUEST AUTHORIZATION TO RETROFIT SHED 2 DOORS
 
Description:
This item seeks Board approval to retrofit 26 loading doors in Shed 2 with integrated physical safety gates and trailer-dock locking systems. Ports America has completed the retrofit of 60 doors, and additional 26 doors are needed to support continued safe and efficient operations. The estimated cost is $442,000.00. Ports America will complete the work and will be reimbursed by MSPA as a responsible lessee. 
 
Subject:
9. ENGINEERING UPDATE
Subject:
10. OPERATIONS REPORT
Subject:
11. EXECUTIVE DIRECTOR'S REPORT
Subject:
12. GENERAL COUNSEL'S REPORT
Subject:
13. MDA COMMENTS
Subject:
14. COMMISSIONERS' COMMENTS
Subject:
15. EXECUTIVE SESSION - LEGAL, REAL ESTATE, AND PERSONNEL MATTER

Web Viewer