June 3, 2025 at 8:00 AM - District 23 Buildings & Sites Committee Meeting
| Agenda |
|---|
|
I. Call to Order
|
|
II. Discussion Items
|
|
II.A. Discussion of Summer 2025 Work
Description:
Amy & Raf will provide updates on several projects that the summer crew will be working on including:
|
|
II.B. Specialty Floors - MacArthur Gymnasium Floor Refinishing
Description:
The proposal for annual services has been attached for the Committee's review.
Attachments:
()
|
|
II.C. Update on Ross/Sullivan Garden
Description:
Amy will provide a brief update on the Garden and the plans for installation this summer.
|
|
II.D. Patriot Paving - Additional Concrete Work
Description:
During the walk-through with the awarded vendor for seal coating and concrete repairs, a few small items were identified that will likely be added to the paving work this summer, including: curbs/bollards at the Sullivan rear entrance, additional asphalt at Schoenbeck bus entry, and one additional square of concrete (Sullivan sidewalk).
|
|
II.E. Required Installation of Fire Rated Doors in the Grodsky Basement
Description:
Following citations from the ROE/Fire Marshall, we will need to install fire-rated doors leading into the Grodsky basement. A proposal has been attached for the Committee's review. Following approval, work will be scheduled over the summer.
Attachments:
()
|
|
III. Adjournment
|