II.A. Update on Summer 2024 Work
Description:
Amy will provide an update on the Summer 2024 work.
|
II.B. Phase 2 - Security Camera Work
Description:
Following the successful Phase 1 camera installation over winter break at Eisenhower and Anne Sullivan, Phase 2 interior camera work will be scheduled at Ross and Sullivan which will include replacement of some of the existing cameras and installation of monitors in each of the main offices of the school buildings. Total cost of the Phase 2 proposed work is $56,220.
Attachments:
(
)
|
II.C. MacArthur Phase 2 - Glycol Return
Description:
Amy will provide an update on the need for additional Glycol in our district-wide geothermal systems.
|
II.D. Access Point - E-rate Update
Description:
Amy will provide an update on the Access Point Replacement that has been budgeted for FY2024 and FY2025.
Attachments:
(
)
|
II.E. Ross - Library Roof Leak Update
Description:
During the mid-January cold spell, freeze and thaw, a small roof leak was detected in the Ross library ceiling. Riddiford Roofing will be visiting this week to make the repair.
|