August 6, 2014 at 7:00 PM - Facilities Committee
Agenda |
---|
I. 2008 BOND PROGRAM & LOCAL CONSTRUCTION PROJECT
|
I.1. Mission High School Phase III Renovation – ERO International
|
I.1.a. Status Report
Attachments:
(
)
|
I.2. Leal Elementary Ramp Enclosures – EGV Architects
|
I.2.a. Status Report
Attachments:
(
)
|
I.2.b. Consideration and Approval of Construction Change Directive # 1 to Re-Route Primary Conduit as
per AEP for the Leal Elementary Ramp Enclosure Project
Attachments:
(
)
|
I.2.c. Consideration and Approval of Change Order #2 for Three (3) Delay Days for the Leal Elementary
Ramp Enclosure Project
Attachments:
(
)
|
I.3. Mission Collegiate High School (MCHS) Project – EGV Architects
|
I.3.a. Status Report
Attachments:
(
)
|
I.3.b. Consideration and Approval of Construction Change Directive # 1 for the MCHS Project
Attachments:
(
)
|
I.4. Mission High School (MHS) Field House Project – EGV Architects
|
I.4.a. Status Report
Attachments:
(
)
|
I.5. Child Nutrition Program (CNP) Expansion Project– PBK Architects
|
I.5.a. Status Report
|
I.5.b. Consideration and Approval of the Ranking of Proposals for the CNP Expansion Project and Approval to Enter into Negotiations in Order of Ranking
Attachments:
(
)
|
I.6. Mission Junior High School( MJHS) and Alton Memorial Junior High School (AMJHS) Canopies- PBK Architects
|
I.6.a. Status Report
Attachments:
(
)
|
I.7. MJHS Kitchen/Dining Addition/Renovations – PBK Architects
|
I.7.a. Status Report
|
I.8. Veterans Memorial High School (VMHS) Cosmetology Lab - PBK Architects
|
I.8.a. Status Report
Attachments:
(
)
|
I.9. MHS Tom Landry and VMHS Stadium Turf and Re-surfacing of the Tracks – Javier Hinojosa Civil Engineering
|
I.9.a. Status Report
|
I.9.b. Consideration and Approval to Grant Administration Authority to Approve Substantial Completion for the MHS Tom Landry and VMHS Stadium Turf and Re-Surfacing of the Tracks Project
Attachments:
(
)
|
I.10. MHS Tom Landry Visitors and Leo Najo Baseball Parking Lots - Javier Hinojosa Civil Engineering
|
I.10.a. Status Report
|
I.11. Elementary Tracks – Javier Hinojosa Civil Engineering
|
I.11.a. Status Report
|
I.12. Cantu Elementary Fire Sprinkler System –Trinity MEP Engineering
|
I.12.a. Status Report
Attachments:
(
)
|
I.13. Tom Landry Stadium Eagle/Patriot Statue
|
I.13.a. Status Report
|
I.14. 2006 and 2008 Financial Update and Qualified School Construction Bond (QSCB) Financial Update
Attachments:
(
)
|
II. Adjournment
|